Commissioning of the Terminal “FSRU Toscana” is proceeding

The commissioning phase of the regasification plant of OLT Offshore LNG Toscana is on going, in line with the company’s operating program. After successful offloading of the first LNG cargo and with the completion of all safety and environmental checks, the Terminal started to regasify the LNG since the beginning of October, exporting, without problems, natural gas in the network of Snam Rete Gas.

Further LNG has arrived, according to the commissioning program. The operations have been performed following to all the environmental and safety prescriptions issued from the competent Authorities (Ministry for the Environment, ISPRA, ARPAT, CTR), in compliance with the dispositions of the Maritime Authority. All these activities are carried on also under the continuous supervision of the Port of Livorno Coast Guard.