Capacity allocation for the current Gas Year

  • 1. Available capacity products

    Select a month:

    August 26th, 2020

    OLT Offshore LNG Toscana informs that on September the 1st, 2020 the offers for regasification capacity products for the Gas Year 2020/2021 offered during the Gas Year can be presented through the PAR according to the times available in the attached calendar.

    Pursuant to Clause 2.1.8.1 of the Regasification Code the planning of Discharge Slots for capacity products will be carried out through PAR on September 3rd, 2020 from 09:30 CET to 12:00 CET.

    OLT Offshore LNG Toscana also specifies that, if both capacity products are awarded, the priority in selection of the Discharge Slots will be given to the successful bidder with the highest auction Price.

    Documents


    July 24th, 2020

    Pursuant to Clause 2.1.8.1 of the Regasification Code OLT publishes here after the capacity products offered from October 2020 up to the end of the Gas Year:

    • Product n. 1, consisting of 10 Delivery Slots, from October 2020 up to September 2021, as follows;
    • Product n. 2, consisting of 5 Delivery Slots, from October 2020 up to August 2021, as follows.

    Documents

    Each Applicant who meets the Service Conditions under Clause 2.1.1 of the Regasification Code shall:

    • sign a Capacity Agreement pursuant to Clause 2.1.10 of the Regasification Code;
    • provide adequate financial guarantees pursuant to Clause 3.1.1.2 of the Regasification Code;

    by hr. 12:00 CET, August 28th, 2020. The offers can be presented through the PAR, on September 1st, 2020 from 09:00 CET to 14:30 CET.

    September 24th, 2020

    Pursuant to Clause 2.1.8.1 of the Regasification Code OLT publishes here after the capacity products offered from November 2020 up to the end of the Gas Year:

    • Product n.1, consisting of 7 Delivery Slots, from December 2020 up to September 2021, as follows;
    • Product n.2, consisting of 2 Delivery Slots, in June 2021 and August 2021, as follows.

    Documents

    Each Applicant who meets the Service Conditions under Clause 2.1.1 of the Regasification Code shall:

    • sign a Capacity Agreement pursuant to Clause 2.1.10 of the Regasification Code;
    • provide adequate financial guarantees pursuant to Clause 3.1.1.2 of the Regasification Code;

    by hr. 12:00 CET, September 29th, 2020. The offers can be presented through the PAR, on October 1st, 2020 from 09:00 CET to 14:30 CET.

    Pursuant to Clause 2.1.8.1 of the Regasification Code the planning of Discharge Slots for capacity products will be carried out through PAR on October 2nd, 2020 from 09:30 CET to 12:00 CET.

    Documents

     

    October 27th, 2020

    Pursuant to Clause 2.1.8.1 of the Regasification Code OLT publishes here after the capacity products offered from December 2020 up to the end of the Gas Year:

    • Product n.1, consisting of 7 Delivery Slots, from December 2020 up to September 2021, as follows;
    • Product n.2, consisting of 2 Delivery Slots, in June 2021 and August 2021, as follows.

    Documents

    Each Applicant who meets the Service Conditions under Clause 2.1.1 of the Regasification Code shall:

    • sign a Capacity Agreement pursuant to Clause 2.1.10 of the Regasification Code;
    • provide adequate financial guarantees pursuant to Clause 3.1.1.2 of the Regasification Code

    by hr. 12:00 CET, October 29th, 2020. The offers can be presented through the PAR, on November 2nd, 2020 from 09:00 CET to 14:30 CET.

    Pursuant to Clause 2.1.8.1 of the Regasification Code the planning of Discharge Slots for capacity products will be carried out through PAR on November 3rd, 2020 from 09:30 CET to 12:00 CET.

    Documents

    November 25th, 2020

    Pursuant to Clause 2.1.8.1 of the Regasification Code OLT publishes here after the capacity products offered from January 2021 up to the end of the Gas Year:

    • Product n.1, consisting of 6 Delivery Slots, from February 2021 up to September 2021, as follows;
    • Product n.2, consisting of 2 Delivery Slots, in June 2021 and August 2021, as follows.

    Documents

    Each Applicant who meets the Service Conditions under Clause 2.1.1 of the Regasification Code shall:

    • sign a Capacity Agreement pursuant to Clause 2.1.10 of the Regasification Code;
    • provide adequate financial guarantees pursuant to Clause 3.1.1.2 of the Regasification Code;

    by hr. 12:00 CET, November 27th, 2020. The offers can be presented through the PAR, on December 1st, 2020 from 09:00 CET to 14:30 CET.

    Documents

    Pursuant to Clause 2.1.8.1 of the Regasification Code the planning of Discharge Slots for capacity products will be carried out through PAR on December 2nd, 2020 from 09:30 CET to 12:00 CET.


  • 2. Allocation of Delivery Slots during the Gas Year

    The User that wants to participate in the allocation of infra-annual capacity shall:

    The Capacity Agreement must be sent by courier or registered letter to the address here below:

    OLT Offshore LNG Toscana S.p.A.
    Palazzo Orlando, Via Gaetano D’Alesio 2
    57126 Livorno
    Att. Michele Tosi

    or by fax to the number +390586210922 and anticipated, in any case, by email to commercial@oltoffshore.it and/or at the PEC address oltcommercial@legalmail.it.

    The offers for infra-annual regasification capacity should be presented through PAR.

    Select a month:

    Monthly allocation of Delivery Slots and Monthly Slots

    Pursuant to the provisions of Clause 2.1.8.2 of the Regasification Code, OLT publishes the Available Delivery Slots for Months M, M+1 and M+2, while from Month M+3 to the end of the current Gas Year OLT will publish the available regasification capacity divided by Monthly Slot.

    Documents

     

    Allocation of spot capacity

    Pursuant to the provisions of Clause 2.1.9.1 of the Regasification Code, OLT publishes the Available Delivery Slots in October Month.

    Documents

     

    Allocation of First Come First Served (FCFS) capacity

    Pursuant to the provisions of Clause 2.1.9.2 of the Regasification Code, OLT publishes the Available Delivery Slots whose Arrival Window is scheduled in the Month of October 2020. The lenght of First Come First Served (FCFS) auction will be from 09:00 CET of September 18th, 2020 to 12:00 CET of September 30th, 2020.

    The reference price may be modified at 10:00 CET of September 21st, 2020 and at 10:00 CET of September 24th, 2020; the price will be modified decreasingly as the delivery date approaches.

    Documents

    Monthly allocation of Delivery Slots and Monthly Slots

    Pursuant to the provisions of Clause 2.1.8.2 of the Regasification Code, OLT publishes the Available Delivery Slots for Months M, M+1 and M+2, while from Month M+3 to the end of the current Gas Year OLT will publish the available regasification capacity divided by Monthly Slot.

    Documents

    Monthly allocation of Delivery Slots and Monthly Slots

    Pursuant to the provisions of Clause 2.1.8.2 of the Regasification Code, OLT publishes the Available Delivery Slots for Months M, M+1 and M+2, while from Month M+3 to the end of the current Gas Year OLT will publish the available regasification capacity divided by Monthly Slot.

    Documents

     

    Allocation of spot capacity

    Pursuant to the provisions of Clause 2.1.9.1 of the Regasification Code, OLT publishes the Available Delivery Slots in December Month. The offers can be presented through the PAR, on November 17th, 2020 from 09:00 CET to 14:30 CET.

    Documents

     

    Allocation of First Come First Served (FCFS) capacity

    Pursuant to the provisions of Clause 2.1.9.2 of the Regasification Code, OLT publishes the Available Delivery Slots whose Arrival Window is scheduled in the Month of December 2020. The lenght of First Come First Served (FCFS) auction will be from 09:00 CET of November 19th, 2020 to 12:00 CET of December 15th, 2020.

    The reference price may be modified at 10:00 CET of November 23rd, 2020; the price will be modified decreasingly as the delivery date approaches.

    Documents